[Audio] Good morning everyone. Project update as of August 9 2024..
[Audio] Breakdown and Remaining Percentage of our project..
[Audio] Based on the accomplishment our project is ahead by 4 days..
[Audio] As of today 270 days have elapsed since the start of the project. We have 155 days remaining to complete the project. As of the latest update the project has achieved 60.43% of the planned milestones and objectives surpassing the projected accomplishment of 59.55%. This represents a positive advancement of 4 days ahead of the planned schedule..
5. [image].
[Audio] Accomplishment photos for Structural Works.
[Audio] Stripping Of Form Enclosure At Second Floor Stair-1 Stiffener Columns. Form Enclosure At Second Floor Stair-1 Lintel Beams..
[Audio] Field Density Test For S O G. Accomplishment Report.
[Audio] Installation Of Formworks For Second Floor Dust Collector Exterior Wall. Installation Of Rebars For Vault Room..
[Audio] Soil Poisoning For S O G Phase 3.. Accomplishment Report.
[Audio] Gravel Bedding At S O G Area 3 And Production Hallway. Installation Of Rebar Mesh For S O G Area-2 Phase 2..
[Audio] Accomplishment Report For Architectural Works..
[Audio] Masonry Works.. MASONRY WORKS. 13.
[Audio] Concrete Topping For Zocalo At Mixing Room 4 5 AND 6..
[Audio] Plastering Of Interior Wall At Staff Dorms..
[Audio] Formblocks Laying At Second Floor Elevator Walls. Chb Laying At Stair-4 Wall Partition..
[Audio] Concrete Pouring Of Stiffener Beam For Stair-1 Enclosure. Backfilling At Ground Floor S O G Phase 4..
[Audio] Plastering At Front Exterior Wall. Installation Of Groove Joints..
[Audio] Plastering At Front Exterior Wall. Chb Laying At Second Floor Perimeter Wall..
[Audio] Formblocks Laying At Second Floor Elevator Area. Zocalo For Warehouse Ramp And Stair..
[Audio] Clearing And Canting At Mezzanine Mixing Room 5 6 AND 7. Zocalo For Warehouse Ramp And Stair..
[Audio] Installation Of Formblocks For Second Floor Elevator Wall. Concrete Pouring Of Zocalo For Warehouse Ramp..
[Audio] Plastering Of Wall For Stair-4 Enclosure. Plastering Of Wall For Ground Floor Hallway..
[Audio] Mock-up For Goods Slide. Chb Laying At Second Floor Rear Perimeter Along Gl: A-b/7.
[Audio] Plastering Of Wall Enclosure At Second Floor Stair-1. Form Enclosure For Lintel Beams At Elevator Walls..
[Audio] Left Side View. Rear Side View.. Accomplishment Report.
[Audio] Right Side View. Front View.. Accomplishment Report.
[Audio] Aluminum Doors And Windows.. ALUMINUM DOORS AND WINDOWS.
[Audio] Installation Of Window Glass Frame At Mezzanine Mixing Room 4..
[Audio] Miscellaneous Steel Works. MISCELLANEOUS STEEL WORKS.
[Audio] Installation Of Rafters And Purlins.. Accomplishment Report.
[Audio] Installation Of Rafters For Roof Framing..
[Audio] Roof Framing Status As Of August 9 2024..
[Audio] Installation Of G I Pipes For Warehouse Ramp And Stair Railings..
[Audio] Installation Of Stainless Steel Railings At Stair-2..
[Audio] Painting Works.. PAINTING WORKS. 36.
[Audio] Application Of Latex Paint At Storage High Ceiling Along Gl: F-g/7-5. Skim Coating At Second Floor Perimeter Wall Along Gl: F-g/7..
[Audio] Skim Coating At Ground Floor Warehouse Area. Skim Coating Of Wall And Columns At Ground Floor Warehouse Area..
[Audio] Skim Coating At Ground Floor Warehouse Area. Painting At Ramp Railings At Ground Floor..
[Audio] Skim Coating At Second Floor Warehouse Area. Skim Coating Of Roof Beams..
[Audio] Application Of Primer Paint For Second Floor Underslab. Skim Coating Of Walls And Ceiling At Ground Floor Area Along Gl: E-g/7-3..
[Audio] Skim Coating Of Wall And Beams At Ground Floor Warehouse Area. Skim Coating Of Beams And Ceiling At Storage Area Along Gl: F-g/7-3..
[Audio] Painting Works Schedule. 43. A PROPOSED TWO STOREY FACTORY AND WAREHOUSE BUILDING PROJECT 41 uilarStB _Bu LOCATION 7 Quezon PAINTING WORKS SCHEDULE JEROMIAH INCORPORATED OWNER AR NEIL JOHN CLARENCE E- ESTEVES UAP CHITECT NUMBER OF DAYS Storage Area Material Recove" LÖiy. Ki*en Room Room Cold Stora# Rmm Room Pack" Azom 2 Nzom 3 Room 4 Packhg Naom 5 Packhg Room 6 R',om 7 Haeny at Area Washhg and Area Fernak Shc.er T Vale Changhg Room Y Shower and Toilet Secw$ Skep" kea STP control Room Room Pump Rcom and Storage Pres&fs Che and StorageEE Rcom Halway at Azea vaing Rcoms 01 02 Vaing Rcoms 03 Miing Vaing Rcoms 05 Vaing Rcoms 06 Rucoms 07 18 18.
[Audio] Painting Works Schedule. 44. A PROPOSED TWO STOREY FACTORY AND WAREHOUSE BUILDING PROJECT 41 uilarStB _Bu LOCATION 7 Quezon PAINTING WORKS SCHEDULE JEROMIAH INCORPORATED OWNER AR NEIL JOHN CLARENCE E. ESTEVES UAP CHITECT NUMBER OF DAYS.
[Audio] Waterproofing Works.. WATERPROOFING WORKS.
[Audio] Application Of Waterproofing Membrane At Mixing Room 1..
[Audio] Jeromiah Procurement Status As Of August 9 2024..
[Audio] Masonry And Plastering Schedule For The Month Of August.