[Audio] Welcome to Nariyah 2 – 1890 Mega Watt - Independent Power Project. This is Visitor Safety Induction training, and it is designed to ensure your safety & wellbeing while visiting and short-term working at the Nariyah 2 project..
[Audio] HEI, as the EPC of NAIRYAH 2 1890MW Independent Power Project, is develop NAIRYAH 2 Power Plant on turnkey basis, located in the Al Nairyah – Eastern province of Saudi Arabia. This project will be one of the largest gas combined cycle power plants installed in Saudi Arabia in recent years. Harbin Electric International Co., Ltd. (HEI), is China's leading large-scale enterprise in power project contracting and export of power equipment. Established in 1983. During the past 42 years, HEI built large power stations on turnkey basis in more than 20 countries with total installed capacity of over 50000MW..
[Audio] The NAIRYAH 2 IPP is situated in the eastern region of Saudi Arabia, approximately 250km and 150km from Dammam city and Jubail industrial city respectively, in the northwest direction. The site is also located 30 km north of Nairyah town. Nairyah has a desert climate. The mean yearly temperature varies from extreme heat (up to 46℃) in summer to mild cold (down to 7℃) in winter. The annual rainfall is approximately 110mm..
[Audio] Project site is approximately 900 meters wide and 790 meters long. Site is accessible via single carriage way (Road 6465) which is located about 1km to the west. This road connects to the Highway 85 which is a dual carriage way located to the south..
[Audio] This is Nariyah 2 IPP layout and following directions like North, South, East and West area highlighted for your reference and note. In case of hearing the Site Emergency Siren/ Alarm you need to stop your work and immediately report to the nearest assembly point. There are 5 assembly point at the Nariyah 2 Project. Number 1 – Project Office Area. Number 2 – Administration Building Area Number 3 – Workshop Area Number 4 – Power block Area Number 5 – Water Treatment Plant Area At each assembly point at Nariyah 2 Project there are designated parking place for the ambulance. Along the project road there are designated pedestrian walkway provided for safe access and egress of the workers & Staff from site. Make Sure that you always use the pedestrian walkway if you are going to the project site by walk. And vehicles at the site should give way to the pedestrian at the intersection points. Inside the Project Area and Inside accommodation camp the Speed limit is 20 Kilometer per hour or below. Outside the Construction Site & In proximity of Nairyah 2 IPP Camp Area, vehicles speed limit is 40 kilometer per hour or below..