[Audio] Required 04 Cranes 120T Period 05Days Tension Tower Suspension Tower Tension Tower Suspension Required 04 Cranes 120T Period 05Days Tension Tower Suspension Tower Tower Tension Tower Required 05 Cranes 120T + 05 Cranes Suspension Suspension 160T -Period Tension Tower Suspension Tower Tower Tower Tension Tower 08Days.
[Audio] Required 05 Cranes 120T + 05 Cranes 160T -Period Tension Tower Suspension Tower Tension Tower 08Days Required 04 Cranes 120T + 04 Cranes Suspension Suspension 160T -Period Tower Tower Tension Tower 05Days Please note that the cranes listed above in this drawing are intended for stringing activities. The cranes required for Erection are provided below. 1- 01 Nos Crane 200T required for 06 days. 2- 01 Nos Crane 160T required for 40 days. 3- 01 Nos Crane 70T required for 45 days..