[Audio] The slide presents the review and approval process for the Pengerang LNGT Security Risk Assessment (S-R-A--) Report. The report was created by Mohd Roslin Mamat reviewed by Norazan Omar and Haji Rahmat Siran then approved by Azaharin Ahmad on March 2024. All four names are present in this table to ensure that due process was met prior to approval of any security risk assessments..
[Audio] petronas has created a Security Policy as an effective security management system for their personnel property information and operations. Policies standards and guidelines have been outlined to ensure a secure environment is maintained. Furthermore petronas encourages security awareness and emphasizes that security is a shared responsibility..
[Audio] As we can see from this slide the objective of this report is to conduct a Security Risk Assessment in the Pengerang Region for the Pengerang LNGT. To do so we will look at the background reference any existing information analyze the methodology and project overview document any incidents in 2023 assess potential threats review the impact of the assessment provide an on-ground assessment and ultimately provide our Security Risk Assessment recommendations and a way forward..
A risk assessment is an important part of any information security process. A risk assessment is used to understand the scale of a threat to the security of information and the probability for the threat to be realized. The result of a risk assessment can be used to prioritize efforts to counteract the threats. The following scenarios illustrate how a risk assessment will assist in making information security decisions. Performing a risk assessment will help determine where to focus resources, when to think about modifying functions, and when to stop using that function as the risks may not warrant corrective action..
To conduct an assessment of potential security risk exposure. To identify potential threats and vulnerability levels to site projects. To propose recommendations for enhancement of security measures. To prevent any potential dangers that have the capability, motivation, and intent to exploit existing vulnerabilities. To protect valuable and sensitive company data, including personal and financial information, from ransomware and data loss. To comply with regulatory standards to prevent lawsuits. To measure the risk ranking for each asset and assess its criticality based on how it would affect business operations; and To secure the company’s reputation and brand image..
[Audio] We visited Pengerang L-N-G-T at the start of this month to assess the security risk upon request from petronas. Engagements with local authorities revealed potential security threats and we shared recommendations and best practices to meet petronas' Minimum Security Standards (M-S-2--). Discussions centered around fishermen incursion and utilization of drones and we outlined strategies to address these and boost security standards within the P-T-2-S-B and Pengerang L-N-G-T regions..
[Audio] The Security Risk Assessment for the Pengerang Region for the March 2024 period has incorporated the Pengerang LNGT Security Risk Assessment (S-R-A--) Report petronas Security Policy petronas Security Management System (SeMS) petronas Minimum Security Standards (M-S-2--) petronas ERM Framework petronas Risk Library ISO 31000: 2009 – Risk Management: Principles and Guidelines and ISO 31010: 2009 – Risk Management: Risk Assessment Technique in order to identify key risks and formulate mitigating measures..
[Audio] Security Risk Assessment (S-R-A--) is an essential part of creating a complete security strategy for the Pengerang L-N-G-T facility group. The S-R-A process helps to identify potential security risks and evaluate them in order to identify appropriate prevention measures that can be put in place to protect the facility. Risk analysis provides the insight needed to determine the vulnerability of the facility and the success of existing or proposed security reduction measures. Lastly risk treatment involves making decisions about which strategies to use in order to minimize the risk by applying security mediation measures and strategies..
[Audio] Pengerang LNGT Security Risk Assessment (S-R-A--) Report Internal is an extensive assessment of the security protocols in place for the Pengerang Region. This report outlines the design of the terminal the plant systems and the design criteria of the security system. It has been created in accordance with the Malaysian Government’s ambition to provide certified shippers the ability to utilise the available capacity of our regasification terminals and pipelines. This move is part of the Malaysian Government’s Third-Party Access framework launched to guarantee and maintain energy supplies for Malaysia’s domestic requirements and economic growth. Those interested in using our facilities can contact us..
[Audio] Pengerang Gas Pipeline connects four key supply points: GPPs TTM Gas Plant Sg. Udang Offshore Regas Terminal and Pengerang LNGT Terminal. Furthermore Pengerang hosts a joint development area that includes a Petrochemical Complex and Power Plant. Pengerang L-N-G-T is the fourth supply point in the region and is the most significant one; it has a capacity of 3.5 M-T-P-A with a flow rate of 490 millimetersscfd. All these points contribute to make Pengerang one of the most important energy hubs in the region..
12. Terminal Layout. Internal. [image]. [image] iii.
[Audio] An overview of the security risk assessment conducted at Pengerang L-N-G-T in March of 2024 is provided in this slide. The assessment encompassed two L-N-G storage tanks with 2 in-tank pumps and 2 re-loading pumps a regasification unit a flare system four HP pumps four O-R-V-s three B-O-G compressors a seawater package with four seawater pumps an L-N-G trucking facility with four loading bays a jetty and two additional L-N-G storage tanks. This extensive audit was carried out to guarantee the safety and security surrounding this area..
14. Internal. Regasification Terminal was assets invested by PLNG2 as part of fast-growing energy and solutions partner for LNG business in the region and globally.
[Audio] This Security Risk Assessment outlines the implementation of a just-in-time field responder program aiming to maximize maintenance strategy and reduce offshore costs. Specifically it describes the renovation of the remote U-O-C upgrades to the Hololens app extension of HoloLens drones and C-C-T-V feed to Microsoft Teams for incident management and remote engineering and improvements to people tracking remote monitoring and engineering capability. Additionally it outlines the relocation and enablement for U-O-C systems integration of remote PMCS/DCS systems wireless comms enablement expansion to the entire terminal and jetty of the DX Fuse application and enhancement of the RGTP 3D model. Also included are the installation of IoT sensors and cameras improved wireless connectivity to the entire terminal and jetty C-C-T-V surveillance and the Virtual Asset Walkabout and Remote Incident Management Scopes. By making use of modern technologies like the Trimble X-R-1-0 with Hololens 2 BuildingPoint Scandinavia and other advancements this Security Risk Assessment will help manage resources and personnel more efficiently and effectively..
[Audio] Security Risk Assessment for the Pengerang Region provides a comprehensive overview of the safety and security practices of the group. This slide outlines the operational parameters for loading and unloading of L-N-G vessels. Maximum vessel length is 345 meters with a beam of 55 meters and a draft of 13.7 meters. Maximum displacement capacity is 206000 tons with a cargo capacity of 260000 cubic meters. Maximum operational flow rate for loading is 12500 cubic meters per hour with a pressure of 100-120 mbarg and return boil off gas parameters are a flow rate of 9000 cubic meters per hour with a temperature of around -120 degrees celsius. Results of this assessment will be highly beneficial in ensuring the safe and secure operation of the L-N-G terminal..
[Audio] The LNG Tank and Open Rack Vaporiser (O-R-V--) are of great importance in assessing the security risks in the Pengerang region. The O-R-V is known for its efficiency in transforming L-N-G from its liquid form to gaseous form without releasing any carbon dioxide. Furthermore it is cost-effective uncomplicated to use and maintain and one of the most dependable technologies for regasifying LNG. From the tanks the natural gas is then routed through measuring stations to customers' facilities..
[Audio] The Pengerang LNGT Security Risk Assessment includes a feedstock pretreatment process consisting of four distinct sections. Clarification is applied to remove larger solid particles for increased plant uptime. Degumming removes phosphorous compounds from the feedstock. Water Washing is done to remove any remaining contaminants before Bleaching and Filtration provide the final pretreatment step. This ensures the feedstock is prepared correctly for the H-E-F-A unit..
[Audio] This presentation focuses on the Security Risk Assessment (S-R-A--) objectives for the Pengerang region. Feedstock pre-treatment plays a key role in the plant's security and overall efficiency of the plant operations. The pre-treatment involves a sequence of steps to remove solid particles phosphorous compounds and other contaminants prior to the plant's High Efficiency Filtration Unit (H-E-F-A-). Undertaking this pre-treatment enhances the quality of the feedstock to reduce the likelihood of potential downtime. Moreover it helps reduce the cost of maintenance and increases the effectiveness of the plant..
[Audio] Security risks posed to the Pengerang L-N-G-T area are discussed in this slide. Two potential risks included are intrusion by hobbyist drones and attacks by militant or terrorist groups. It is assessed that the risk of intrusion by hobbyist drones is at a medium level while the risk of attack by militant or terrorist groups is low. A low medium and high threat rating range is presented with the low range being 0 to 7 medium range being 7 to 18 and high range for 66 and above. Through this assessment the goal is to ensure the security of the Pengerang L-N-G-T area..
[Audio] The Security Risk Assessment (S-R-A--) report outlines two security threats specific to the Pengerang L-N-G-T installations. The first of these is unauthorized entry to the office processing area and restricted area. It has been assessed as having a low risk due to the security measures taken including total security manpower and physical security running along the perimeter. The second threat is the potential encroachment of the marine facilities such as the Jetty and Port. The potential hazard to vessels and infrastructure has been deemed to have a low risk due to the mitigation measures in place by Pengerang L-N-G-T management and the use of Marine Auxiliary Police to protect the jetty and port..
[Audio] This slide is about Security Risk Assessment in the Pengerang Region. It evaluates the risk levels associated with certain types of crime. For theft from office or street crime the threat rating is L-O-W which is a part of the low risk range. This range is made up of 0 to 7 out of the total 66 points in the High range. To summarize this slide shows that theft from office or street crime is considered a low risk..
[Audio] A Security Risk Assessment (S-R-A--) for the Pengerang region is of vital importance. The report revealed the risk levels to range from low (3-7) medium (7-18) to high (66 and above). In terms of threats to the Pengerang LNGT Airspace the most likely consequence of a hobbyist or civilian commercial drone is disruption or suspension of operations. However the design spacing construction material and strength of infrastructure has reduced the risk of damage. Should a terrorist or militant group employ a drone with a high-powered explosive or fuel payload it could cause extensive fire explosions disruption of business operations and potential fatalities and injuries. It is essential that this security risk assessment is closely followed in order to guarantee the safety of all individuals in the area..
[Audio] I am presenting the Pengerang LNGT Security Risk Assessment Report (S-R-A--). This report focuses on the risks and threats posed by trespassing and unauthorized entries as well as encroachment of marine facilities such as Jetty/Port. There have been no recorded cases of trespassing or unauthorized entry since the commencement of operation but the risk is still present and needs to be addressed. Small commercial vessels leisure craft or fishermen in small boats fishing in traditional 'fishing waters' may encroach on and/or enter the exclusion safety zone and cause a hazard to petronas/contractor’s facilities. This could be detrimental and create an unconducive environment. The impact of these security risks is assessed as Moderate and it is essential that proper measures are put in place to guard against any potential threats generated by these factors..
[Audio] This S-R-A report examines the security risk posed by theft from offices and street crime. Break-ins theft and robbery from worksites offices and commercial buildings as well as petty crime street mugging and assault on the street can cause a moderate risk to the security of the region. Appropriate security procedures should be implemented to reduce the potential risks posed by criminal activity..
[Audio] After an evaluation of Pengerang L-N-G-T on the 15th of March 2024 it was found to generally have a favorable security situation. The L-N-G-T located between Tanjung Kapal and Tanjung Ayam is 115 kilometers from Johor Bahru and delivers natural gas with a maximum pressure of 68.95 Barg and a minimum temperature of 15°C with a 98% availability. Additionally a L-N-G unloading/reloading berth is located at a nearby Jetty owned by Pengerang Terminals (Two) Sdn Bhd and is equipped with the necessary process and safety equipment. Pengerang L-N-G-T is currently in the process of obtaining an 'OGA Permit' from the Marine Department of Malaysia..
On Ground Assessment. Main Gate Entrance. A road with a building and cones.
On Ground Assessment. A road with a gate and fence Description automatically generated.
On Ground Assessment. Fencing. A fenced in area with gravel and wire Description automatically generated with medium confidence.
Security Risk Assessment. Internal.
[Audio] Security risk assessment report for the Pengerang L-N-G-T in Malaysia has identified five main risks intrusion into airspace by hobbyist and civilian drones attack by militant or terrorist groups trespassing and unauthorized entry fishing activities and theft from the office street crime and other facilities. It is essential that a thorough assessment of the risks related to these issues is carried out in order to provide adequate protection of Pengerang L-N-G-T as well as those who visit the area..
[Audio] We identified five potential risks that could affect Pengerang L-N-G-T and its operations during our Security Risk Assessment: intrusion into Pengerang L-N-G-T airspace potential attack by an armed group unauthorized entry into office process area and restricted area fishing activities around marine facilities and theft from offices. Brownfield mitigation and other recommendations have been put in place to address these risks but we need to ensure that these measures are implemented to ensure the security of Pengerang L-N-G-T and its operations..
[Audio] In order to ensure the security of the Pengerang region it is recommended to install lighting barriers signage and other traffic calming measures at entry and exit points. Furthermore outdoor parking areas should be adequately lit and utilities and equipment rooms should be kept locked and secured when not in use. These security measures are essential in guaranteeing the safety of the region..
[Audio] The Security Risk Assessment (S-R-A--) for the Pengerang Region will ensure that measures are put in place to protect against physical security threats. This includes implementing an approved Site Security Plan as well as written Standard Operating Procedures for security operations. Additionally staff visitors and contractors will receive briefings and awareness sessions about potential drone and maritime intrusions. Signage should also be installed to clearly warn the public about these security restrictions. Lastly a H-S-E risk assessment will be conducted to ensure safety and rising arm barriers will be installed to protect against unauthorized vehicle access. All of these measures are planned to be completed in the fourth and first quarters of 2024 and 2025 respectively..
[Audio] The Security Risk Assessment (S-R-A--) for the Pengerang Region identifies the necessity of increased safety measures like increased lighting perimeter fencing and a dedicated security monitoring room. These improvements offer an increased level of security for areas such as material storage staging building materials projects as well as parking and machinery. It is recommended that the lighting be implemented in Q1 2020 perimeter fencing in Q2 2020 and the security control room in Q3 2020 by Pengerang LNGT. This report highlights the need for these safety enhancements to secure a secure working environment for all involved..
[Audio] A security risk assessment of the Pengerang L-N-G-T facility has identified areas of concern that require attention. This presentation outlines a number of recommendations to enhance perimeter security parking areas and the building/plant. These include installing video surveillance cameras of different image types electronic access control systems and door sensors with audible or visible alarms to monitor each of these areas. It is expected that the recommendations will be implemented by the end of quarter 2 of 2026..
[Audio] This S-R-A report for the Pengerang Region is a vital tool to recognize potential security issues and suggest suitable safety measures to protect personnel equipment and assets. As indicated in the table it is advised to install additional Video Surveillance Systems (V-S-S--) at the entry of the project site the site office each zone area and the warehouse/laydown/yard. The V-S-S should be in open view to act as a deterrent for criminal activity and to give assurance to staff. Furthermore the V-S-S system and all cameras should be in full working order with high resolution day/night cameras additional visible or infrared lighting and battery backup to keep operations running in case of main power failure. Additionally all cameras should be positioned in a way that makes them difficult to move or tamper with and the cabling should be tucked away. By following these steps we can make sure that effective security protocols are in place with minimum disruption to operations..
[Audio] The Security Risk Assessment (S-R-A--) Report carried out within the Pengerang Region proposes an overview of security recommendations and timelines for implementation. This slide lists topics related to security technology and technology along with the recommendation timeline for implementation and parties involved. These include the implementation of an Access Control System (A-C-S--) from the security control room or a workstation in the main office and installation of communication devices to ensure safety and security. Adhering to these recommendations will enable our organization to ensure the safety and security of the Pengerang Region..
[Audio] Pengerang LNGT Security Risk Assessment Report is an evaluation of the security protocols in the Pengerang Region. It contains details of the recommended security measures their timeline for implementation and findings from the assessment. The report suggests increasing the security personnel at the entrance/exit gate for access control and regular patrolling of the perimeter and surrounding areas. In the event of any security issues immediate reporting to a supervisor or company representative is recommended. Furthermore if any oversize material is entering or leaving the project site Auxiliary Police from Group Security armed with set procedures should be present..
[Audio] The slide focusing on the security risks associated with the Pengerang L-N-G-T facility in March 2024 displays the specific areas of concern recommended actions timeline and the party responsible for each recommendation. Regarding security organisation it is recommended that the facility deploys an in-house guard force or licensed security guard force to protect the site with a management team to oversee and manage security operations. This team should also ensure that all security personnel have uniforms P-P-E and other security equipment and are competent in their security duties. The building/plant owner is responsible for the successful implementation of the security risk assessment for the facility..
[Audio] The importance of securing our workplace cannot be overstated. To this end this Security Risk Assessment Report is intended to provide a framework for safeguarding personnel and assets by implementing standardized security procedures. These procedures include access card systems for building and plant owners contractors vendors and visitors emergency response plans gate pass procedures and communication systems with both internal and external parties. Adhering to these regulations will help ensure that the region remains safe and well-protected..
[Audio] The slide puts forward the security measures which require planning for implementation. An in-depth analysis of the potential risks associated with the Group Security Pengerang Region is provided in this S-R-A report in order to guarantee safety and security. The suggested measures tackle the recognised security risks and will help protect and safeguard the Pengerang L-N-G-T facility..
[Audio] S-R-A is conducted to evaluate the possible security risks in the Pengerang region. Analysis and comparison between existing and suggested security risk matrices will be done in order to determine the most suitable measures to maintain security in the region. This will guarantee protection and security of citizens infrastructures and resources located in the Pengerang region..