Raft - Construction joint with Internal Sika Waterbar ® Installation steps

A picture containing building, building material, coffee table Description automatically generated

Scene 3 (20s)

Installation steps:

2- Add first cast of structural concrete to raft foundation

3- Add Sika Waterbar ®

4 – Finalize second and third cast of the raft .

1 - Install Sika ® Waterproofing Membrane

Scene 4 (35s)

Sika Waterbar® Construction joint (structural)

First cast structural concrete is placed to the half of the internal Sika Waterbar® on to the Sika® Waterproofing Membrane

Sika® Waterproofing Membrane

Scene 5 (48s)

Sika Waterbar® Construction joint (structural)

Raft - First Cast

Sika® Waterproofing Membrane

Scene 6 (56s)

Sika Waterbar® Construction joint (structural)

Sika Waterbar ®

Raft - First Cast

Sika® Waterproofing Membrane

Scene 7 (1m 4s)

Sika Waterbar® Construction joint (structural)

Sika Waterbar ®

Raft - First Cast

Sika® Waterproofing Membrane

Remember:

Concave shape facing upwards.

Add at middle height .

Scene 8 (1m 16s)

Raft (structural – second Cast)

Second cast structural concrete is placed to the Sika® Waterproofing Membrane. When casting concrete pay special attention to the area where Sika Waterbar ® is installed

Raft - Second Cast

Scene 9 (1m 31s)

Raft – Connection with Sika Waterbar® (Construction joint)

Sika® Waterproofing Membrane

Sika Waterbar ® (installed in concave shape)

Raft - First Cast

Raft - Second Cast

Scene 10 (1m 45s)

A picture containing building, building material, coffee table Description automatically generated

Raft – Connection with Sika Waterbar® (Construction joint)

Sika® Waterproofing Membrane

Sika Waterbar ® (installed in concave shape)

Raft - First Cast

Raft - Second Cast