Smart Grid Pilot Project Under DPDC. A journey towards Smart Bangladesh.

Scene 2 (10s)

Project Implementation period:. Project Start Date Project Completion Date (extention will be needed) 01.07.2020 30.06.2025.

Scene 3 (37s)

Component 1: (EUR 100 million) - Power Factor Improvement financed by AFD loan.

Scene 4 (1m 18s)

Objectives of Smart Grid in DPDC. ✔️ To improve the quality of power supply (power factor improvement) ✔️ To enhance the reliability of supply ✔️ To increase redundancy in the distribution network ✔️ To reduce system losses ✔️ To strengthen accountability and transparency ✔️ To enhance operational flexibility for efficient power distribution ✔️ To increase customer engagement ✔️ To align with the mission and vision of DPDC.

Scene 5 (1m 36s)

Expected Outcomes of Smart Grid Project. ✅ More stable and high-quality electricity supply ✅ Reduced power outages and improved service continuity ✅ Enhanced grid resilience with redundancy in the network ✅ Lower technical and non-technical losses ✅ Implementation of self-healing of Network through FLISR technology ✅ Improved customer satisfaction and interaction ✅ Strengthened governance with better accountability and transparency ✅ Achieving DPDC’s long-term mission of a modernized power system.

Scene 6 (1m 55s)

Prominent Housing Nabinagar Housing Ramchandrapur Road 6 Avenue Road 2 Society PC Culture Housing Society Muhammadia 00 mad Zia Uddan Lackpar Road Sanqshad Bhaban Lake anma Shaheenbag Nakhi Tejkuni Para Indira RD-—- - b gan.

Scene 7 (2m 13s)

line connector. line connector. line connector. line connector.

Scene 8 (2m 48s)

PRESENT OPERATIONAL PROCEDURE OF 11KV OVERHEAD FEEDERS.

Scene 9 (2m 55s)

Satmasjid 33/11 kV Substation. Asad Gate 33/11 kV Substation.

Scene 10 (3m 9s)

Satmasjid 33/11 kV Substation. Asad Gate 33/11 kV Substation.

Scene 11 (3m 25s)

SMART GRID: ADMS Functionality on 11KV Overhead Feeders.

Scene 12 (3m 33s)

Satmasjid 33/11 kV Substation. Asad Gate 33/11 kV Substation.

Scene 13 (3m 52s)

Satmasjid 33/11 kV Substation. Asad Gate 33/11 kV Substation.

Scene 14 (4m 13s)

Fault Occurs. Satmasjid 33/11 kV Substation. Asad Gate 33/11 kV Substation.

Scene 15 (4m 37s)

Satmasjid 33/11 kV Substation. Asad Gate 33/11 kV Substation.

Scene 16 (4m 47s)

Fault Occurs. Satmasjid 33/11 kV Substation. Asad Gate 33/11 kV Substation.