[Audio] Current Activities As Of January 28, 2021 Current activities as of january 28, 2021.
[Audio] Plumbing Plumbing. PLUMBING.
[Audio] Installation Of Plumbing Fixture 4th Floor Intallation of plumbing Fixture at 4th floor.
[Audio] 2nd Floor Installed Remaining Water Closet Shower Fixture Bidet Floor Drain & Shower Drain Clean Out Lavatory Bathtub.
[Audio] 3rd Floor Installed Remaining Water Closet Shower Fixture Bidet Floor Drain & Shower Drain Clean Out Lavatory Bathtub.
[Audio] 4th Floor Installed Remaining Water Closet Shower Fixture Bidet Floor Drain & Shower Drain Clean Out Lavatory Bathtub.
[Audio] Tabulation 2nd Floor. TABULATION 2ND FLOOR.
[Audio] Tabulation 3rd Floor. TABULATION 3RD FLOOR.
[Audio] Tabulation 4th Floor OK OK OK OK OK OK OK OK OK OK OK OK.
[Audio] Fire Protection. FIRE PROTECTION.
[Audio] Rectification Of Fire Pro Droppings @ Basement 1 (common Toilet).
[Audio] Remaining Works(pl/s) Basement 3 Basement 2 -all Works Done -installation Of Plumbing Fixtures Basement 1 Lower Ground Floor -installation Of Plumbing Fixtures -installation Of Plumbing Fixtures 2nd To 4th Floor Upper Ground Floor -installation Of Plumbing Fixtures -all Works Done -installation Of Water Meter Roof Deck 5th Floor -installation Of Plumbing Fixtures -all Works Done -installation Of Water Meter.
[Audio] Remaining Works(fp) Basement 3 Basement 2 -all Works Done -all Works Done Upper Ground Floor Basement 1 -all Works Done -fdc Plate & Cap W/ Chain Installation -relocation Of Droppings Lower Ground 2nd Floor -all Works Done -all Works Done.
[Audio] 3rd Floor 4th Floor -all Works Done -all Works Done 5th Floor Roof Deck -final Droppings -all Works Done.
[Audio] Thank You!. THANK YOU!.