CLIMATE SMART IRRIGATED AGRICULTURE PROJECT (CSIAP) MINISTRY OF AGRICULTURE (MOA) DPD Office – North Western Province

Published on
Embed video
Share video
Ask about this video

Scene 1 (0s)

CLIMATE SMART IRRIGATED AGRICULTURE PROJECT (CSIAP) MINISTRY OF AGRICULTURE (MOA) DPD Office – North Western Province.

Scene 2 (10s)

Content :. Project contribute to SDG Total Project Allocation(6Provinces) Project Objectives Stakeholders in the Project General Information in NWP CSIAP Road Map Implementation Progress Allocation for 2025 Video for Past Project Performance End.

Scene 3 (22s)

Commitment of Sri Lanka to Combat Climate Change Impact Take Urgent Action to Combat SDG No 13 Climate Change and Its Impacts Strengthen resilience and adaptive capacity Integrate climate change measures into policies and planning Improve education, awareness- raising and human/ institutional capacity.

Scene 4 (34s)

Project Allocation for entire project Area (6 provinces).

Scene 5 (1m 0s)

CSIAP- Project Development Objectives (PDO).. Improve the Productivity, Improve the Climate resilience of small-holder agriculture in selected hotspot areas..

Scene 6 (1m 10s)

Key Points :. 1. Hotspot area: Farmers and farming livelihoods are highly exposed and vulnerable to increasing climatic variability. Based on : (a). Drought and Flood impacts. (b). Current climate vulnerability. (C). Future climate vulnerability up to 2030..

Scene 7 (1m 25s)

2. Climate resilience:. Capacity of agricultural systems to respond to drought and flood by resisting or tolerating the impact and recovering quickly, through integration and adaptation, mitigation, and other climate-smart agriculture(CSA) practices.

Scene 8 (1m 44s)

Project Out come Indicators. • KPI 1: Cropping Intensity (%) • KPI 2: Share of Non-Paddy crops in the command area (%) • KPI 3: Area under improved CSA practices (Ha) • KPI 4: Direct project beneficiaries (Total number) • KPI 5: Direct project beneficiaries (Female number).

Scene 9 (1m 59s)

PRA for Need Assessment.. Participatory Rural Appraisal (PRA) Process PRA is conducted to identify and validate potential tanks for rehabilitation and Need Assessments in Project Intervention Key stakeholders involved: Farmers Divisional Secretary / Authorized Executive Officer Divisional Officer (Department of Agrarian Development - DAD) Agriculture Research and Production Officer (ARPO) Grama Niladhari Project Officers.

Scene 10 (2m 15s)

Stakeholders for Project Implementation. Chief Secretary Office Provincial Agriculture Ministry Department of Agrarian Development Provincial Department of Agriculture Provincial Department of Irrigation Provincial Department of Engineering.

Scene 11 (2m 26s)

Community Base Organization to Project activities.

Scene 12 (2m 35s)

General Information(NWP).

Scene 13 (2m 40s)

HOTSPOT AREA IN NWP o 10 Oya 20 Legend Mi_Oya Kala_Oya Nawagaththegama PolpithOama Vanathavdluwa Karuwalagaswewa Girbawa Ehetuwewa Amba npola Oya Km.

Scene 14 (2m 47s)

General Information-Kurunegala. Description Units Ambanpola Ehetuwewa Galgamuwa Galgamuwa Mahananneriya Thambuththa Rajanganaya Maragollagama Rambe Total General Information Electorate Yapahuwa Galgamuwa Yapahuwa DSD Ambanpola Ehetuwewa Galgamuwa Giribawa Polpithigama GND No 17 5 3 3 12 4 6 1 51 Village No 111 31 19 14 40 22 41 6 284 Cascade No 19 2 1 2 3 0 1 1 29 Tanks No 83 10 8 11 77 12 6 207 Farmer Families No 5836 2607 2094 5198 2836 18571 Population No 16188 7658 6592 16188 8562 55188.

Scene 15 (3m 8s)

General Information-Puttalam. General Information Puttlam District Total Electorate Units Anamaduwa Puttlam Anamaduwa DSD Nawagaththegama Wanathawilluwa Karuwalagaswewa 3 ASC Nawagaththegama Wanathawilluwa I/Puliyankulama Pu/Thabbowa 4 GND No 6 5 5 3 19 Village No 43 8 10 11 72 Cascade No 2 1 0 1 04 Tanks No 12 8 0 9 29 Farmer Families No 2519 1588 1639 5746 Population No 7588 5328 4206 17122.

Scene 16 (3m 26s)

CSIAP Roadmap. 2019 - 2020. 2021. 2022. PRA HSAADP Plan PS Formation CSA Training Start CVDP, Yala, Mid & Maha Cultivation Programs Engineering Survey Formation of PSC & DSC.

Scene 17 (3m 52s)

Implementation Progress of The Project.

Scene 18 (3m 58s)

PROGRESS SUB-COMPONENT 1.1 Agriculture Production.

Scene 19 (4m 4s)

Climate Smart Agriculture Practices. 1.Crop Diversification 2.Micro Irrigation 3.Home Gardening 4.Seed Production 5.Inter Season Cultivation 6.Agronomic Intervention.

Scene 20 (4m 16s)

1.CSA Practices' -2020-2024. VS:60 -OF/ZL,'ZZOWQ NO.

Scene 21 (5m 9s)

Equipment Distribution -2024. No Equipment Qut. Purpose 1 Drip irrigation unit 25 (for Fruit) 2 Drip irrigation unit 59 (for vegetable) 3 Sprinkler Jets 64 Bana cultivation 4 Insect proof nets 100 5 Poly mulch 165 6 Solar water pumps 33 7 High pressure Water pump 10 8 Electrict Water Pump 84 9 Fuel water pump 64 10 Tarpaulin 500.

Scene 22 (5m 28s)

Argo-Well Distribution. ASC 2021 2022 2023 Total (Target) Progress Expenditure Rs. (Mn.) Kurunegala 11 34 23 58 58 45.5 Puttalam 3 4 5 12 12 Total 14 38 28 70 70.

Scene 23 (5m 40s)

Crop Diversification under Argo-well (70 Nos.).

Scene 24 (5m 47s)

Ex : Increases of Farmers’ Income under Agro-well Rehabilitation.

Scene 25 (6m 55s)

Out-Come of cultivation under Agro-wells. No. of wells Production (Mt) Production Cost(Rs.) Income(Rs) Net Profit(Rs) Crop cultivated 9 329 5,591,000.00 32,442,300.00 26,851,300.00 Pumpkins, Watermelon, Maize, Paddy, Chili, Manioc, Brinjals, Tomato.

Scene 26 (7m 12s)

Solar water pump Irrigation (45 Nos.).

Scene 29 (7m 31s)

[image] PROGRESS SUB-COMPONENT 1.2 Agriculture Marketing.

Scene 30 (7m 38s)

Marketing Infrastructure. Item Targeted no Completed Cost(Mn) Remarks Agri Roads 15 4 (4.6 km) 2.9 Completed ASC Modernization 8 8 31.5 Completed Agro-wells 70 70 45.5 Completed Solar Powered Cold storage 01 01 7.0 Established at Medagama Farm in DOA Tarpaulins 500 500 11.38 500 tarpaulins were distributed among PSs (average 3 for 1 PS).

Scene 31 (7m 56s)

Progress of Seasonal Cultivation Fence. ASC No.of fence Maha 23/24 Area (Ha) Length(Km) Kurunegala 42 807 136 Puttalam 23 281 49.4 Total 65 1088 185.

Scene 32 (8m 18s)

Out-Come of Cultivation Fence established. ASC No. of Yaya Crop damage before the Project(Ac) Crop Production Before the Project(Kg) Compensation given(Rs.) Ehetuwewa 12 27.3 478,200 976,000.00 Galgamuwa 12 51.75 523,000 2,070,000.00.

Scene 33 (8m 42s)

Ehetuwewa ASC - Crop Damage & Compensation given Before the Project.

Scene 34 (9m 33s)

Cultivation Progress After Project. No GND Name Of FO Name of the Yaya No.of Farmer families Extent cultivated (Ac) Crop name cultivated Crop damage due to Elephant attacked (Ac) Production (Kg) (23/24 maha) Compensation given for damages (Rs.) GPS Cordinates 1 119 - Rathnadiulwewa "Dimuthu" FO Urapolayagama 7 26.67 Paddy 0 41700 0 7.941414/80.321929 2 115 - Ihala Digana "Parakum" FO Bamunugama wewa yaya 25 35.56 Paddy 0 57318 0 7.978799/80.36104 3 110- Mudiyannegama "Ekamuthu"FO - Mudiyannegama Galewewa 56 53.35 Paddy 0 86400 0 7.978869/80.394813 4 113- Makulawa "Perakum" FO Mahawewa yaya 90 56.31 Paddy 0 91300 0 7.988433/80.350993 5 116 - Nithogama Sulugowi Heenkendewa 15 14.82 Paddy 0 23300 0 7.947681/80.340011 6 118- Ethinimale "Samagi"FO Pahalagama yaya 12 26.67 Paddy 0 42700 0 7 114- Nithalawa Gramiya sanwardana Kuda nithalawa 42 35.5 Paddy 0 57200 0 7.980930/80.341830 8 117- Galapitadigana "Perakum" Ihalawewa yaya 15 7.41 Paddy 0 11100 0 7.959939/80.333296 9 110- Mudiyannegama "Samagi" Thanahene yaya 43 39.52 Paddy 0 63700 0 7.975939/80.383390 10 115- Ihala Digana "Perakum" Palugahawewa yaya 30 22.72 Paddy 0 36260 0 7.972862/80.347468 11 119- Rathnadiulwewa " Dimuthu" Ihalawewa yaya 16 13.83 Paddy 0 21600 0 7.948275/80.333322 12 118- Ethinimale "Mahasen" Kudagalawewa yaya 14 11.36 Paddy 0 18630 0 7.952366/80.321326 Total 551,208.

Scene 35 (10m 33s)

No ASC Season Company name Crop No.of Farmers Extent(Ac) Unit Price of selling(Rs.)/Kg Sold amount(kg) Income(Rs) 1 Rambe SR Bio Food (Pvt) Jumbo Peanut 13 10 450 5226 2,351,700.00 2 Rambe SR Bio Food (Pvt) Banana 18 10 90 243876 11,943,895.00 3 Thambuththa Doll Lanka (Pvt)Ltd Banana 18 15 120 40883 2,052,500.00 4 Rajanganaya 23/24 Maha Plenty Food (Pvt) Maize 19 34 135 40,000 5,400,000.00 5 Thambuththa 23/24 Maha Plenty Food (Pvt) Maize 3 3 135 6300 850,500.00 6 Ambanpola Economic centre(Thambuthegama) Nai-Miris 4 1 800 2200 1,760,000.00 7 Ihala Puliyankulama Archiri Fruit (Pvt) Ltd. Passion Fruits 19 15.75 500-700 17,905 7,550,727.00.

Scene 36 (11m 11s)

Cascade & CSIAP Institutional Foundation of NWP.

Scene 37 (11m 18s)

CSIAP Institutional Foundation of NWP. Name Target Progress 01 Producer Societies Producer Associations 230 12 230 12 02 SAC 167 167 03 CMC 21 21 04 FO 125 125.

Scene 38 (11m 29s)

Cascade Management Committee Formation.. Objectives of Establishing Cascade System Management Committees: Institutional Framework: Coordinate management of natural resources (soil, water, forests, etc.). Water Supply Management: Ensure sustainable use for agriculture, livestock, and fisheries. Community Participation: Engage stakeholders in system maintenance. Legal Structure: Establish formal recognition for sustainable cascade management..

Scene 39 (11m 47s)

Key Functions of the Cascade Management Committee..

Scene 40 (12m 4s)

Responsibilities of the Cascade Management Committee.

Scene 41 (12m 22s)

GNDs in Palapathwala Cascade: 1.Plalapathwala 2.Waragammana.

Scene 42 (12m 31s)

Progress of Tank Rehabilitation Phase-1.

Scene 43 (12m 37s)

PUTTALAM VAVUNIYA ANURADHAPURA POLONNAR KURUNEGALA 10 km KANDY NUWARAE.

Scene 44 (12m 51s)

No. of Approved Tanks by World Bank 145. Kurunegala District – 116 Puttlam District - 29 Cascade : Kurunegala -18 Puttalam District -03.

Scene 45 (13m 1s)

Pahala Giribawa Wewa (Downstream Development). [image].

Scene 46 (13m 8s)

Dunhenegama Wewa. A dirt road with trees in the background Description automatically generated.

Scene 47 (13m 21s)

Capacity Increased in Tanks After Rehabilitation.

Scene 48 (13m 40s)

Tanks Financial Progress (2023-2024). Remarks Contract Amount (LKR) Without VAT Total Expenditure F. Progress Total No of Tanks Completed Phy. Progress Kurunegala 1,345,757,522.14 1,047,837,124.16 67.92% 116 116 100% Puttalam 473,176,005.54 414,356,404.71 76.15% 29 29 100% NWP 1,818,933,527.68 1,462,193,528.87 70.07% 145 145.

Scene 49 (14m 4s)

Tank Rehabilitation Phase-2.

Scene 50 (14m 10s)

ASC Tanks Estimated Cost(Rs) Kurunegala 29 669.443 Puttalam 09 154.659 Total 38 824.103.