[Audio] House Construction Report Total Number of Units is 812 Units, 327 are already completed, 210 units are on going and 255 units are still pending.
TOTAL T.O. : 0 UNIT TOTAL M.I. : 0 UNIT TOTAL PIF INSPECTED UNITS : 0 UNIT BASIC LAND DEVELOPMENT- 86% EARTHWORKS – 98% ROADWORKS - 75% STORM DRAINAGE SYSTEM - 96% WATER DISTRIBUTION – 75%.
9/4/2023. UPDATED LAND DEV & HOUSECON MAPOUT. LUMINA SUBIC MAPOUT ADMIN ORDER JUNE 2023 CONSO-1.
9/4/2023. MAP-OUT LAND DEVELOPMENT. LUMINA SUBIC MAP-1.
9/4/2023. GRASSCUTTER MONITORING. MHI LOGO. PROJECT SITE DATE DESCRIPTION QTY UoM REMARKS LUMINA SUBIC 6/28/2023 GRASSCUTTING 10.00 L PHASE 1 BLK 5 LOT 1-35,PHASE 3 BLK 2A LOT 1-20 LUMINA SUBIC 6/26/2023 GRASSCUTTING 10.00 L FABRICATION, WAREHOUSE, BARRACKS LUMINA SUBIC 6/23/2023 GRASSCUTTING 10.00 L FABRICATION, WAREHOUSE, BARRACKS LUMINA SUBIC 6/20/2023 GRASSCUTTING 10.00 L PHASE 3 BLK 12A LOT 1-10 LUMINA SUBIC 6/17/2023 GRASSCUTTING 10.00 L PHASE 3 BLK 12A LOT 11-20 LUMINA SUBIC 6/13/2023 GRASSCUTTING 10.00 L PHASE 3 BLK 3A LOT 1-13 LUMINA SUBIC 6/10/2023 GRASSCUTTING 10.00 L PHASE 3 BLK 4A LOT 1-16 LUMINA SUBIC 6/7/2023 GRASSCUTTING 10.00 L PHASE 1 BLK 10 LOT 31-59 LUMINA SUBIC 6/4/2023 GRASSCUTTING 10.00 L PHASE 1 BLK 10 LOT 1-30.
LAND DEVELOPMENT. 09/12/2022. 09/12/2022. 06-25-2023.
SUBDIVISION MARKER. 09/12/2022. 09/12/2022. 06-25-2023.
SPINE ROAD. 09/12/2022. 09/12/2022. 06-25-2023. 06-25-2023.
MODEL HOUSE. 09/12/2022. 09/12/2022. 06-25-2023. 06-25-2023.
STAFF OFFICE. 09/12/2022. 09/12/2022. 06-25-2023.
WAREHOUSE. 06-11-2023. 06-11-2023. 06-11-2023.
FABRICATION. 09/12/2022. 09/12/2022. 06-25-2023. 06-25-2023.
GRASSCUTTING MONITORING. 06-10-2023. 06-15-2023.