INTERNATIONAL CITY E-18. 1%. PLOT NO. 204 - WARSAN 4.
WORKPLAN OVERVIEW. FOR THE MONTH OF DECEMBER. HOSE RAIL INSPECTION.
COMPLETED WORKS. FIRE AND SAFETY. AS OF DECEMBER 12, 2025.
DOCUMENTS. WE ARE CURRENTLY WAITING FOR THE EXTERNAL INTERLOCK FACILITIES APPROVAL FROM TRAKHEES. THE APPROVAL PROCESS IS STILL IN PROGRESS..
ENGR. MOHAMED. FIRE&SAFETY. All civil works for Fire and safey are complete. Fire cabinets for all floors were installed..
WATER TANK. Water tanks have been delivered and installation is complete..
LIFT. ELECTRICAL. PLUMBING. GREEN BUILDING. CABLES.
ENGR. MOHAMED. GREEN BUILDING. Status Details:. AS BUILT ARCH & HVAC WILL BE SUBMITTED TO GREEN BUILDING CONSULTANT GLOBAL TECH FOR REVIEWING AND SUBMIT TO TRAKHEES.
ENGR. BURHAN. CABLE WORKS. Status Details:. CABLE WORK HAS NOT YET STARTED FROM DEWA, AND WE ARE CONTINUING WITH OUR LV PANEL WORKS AND AS DEWA ENGINEER CABLE WORK WILL BE START END OF JAN.
ENGR. BURHAN. PLUMBING WORKS. Status Details:. PLUMBING WORKS ARE COMPLETED, AND WATER PUMP INSTALLATION IN THE GROUND FLOOR AND ROOF IS PENDING. AS PER THE PLAN, PLUMBING WORKS WILL BE COMPLETED BY 20-12-2025 (EXCEPT ACCESSORIES)..
ENGR. BURHAN. ELECTRICAL WORKS. Status Details:. MAJOR ELECTRICAL WORKS WILL BE COMPLETED SOON. LV ROOM WORKS ARE ONGOING..
ENGR. BURHAN. LIFT. Status Details:. LIFT WORK COMPLETED ONLY INSIDE MARBLE WORK AND TESTING & COMMISSIONING.
NEXT WEEK’S DELIVERABLES. 15 DECEMBER 2025 MONDAY 16 DECEMBER 2025 TUESDAY 17 DECEMBER 2025 WEDNESDAY 18 DECEMBER 2025 THURSDAY 19 DECEMBER 2025 FRIDAY 20 DECEMBER 2025 SATURDAY 21 DECEMBER 2025 SUNDAY.