PowerPoint Presentation

Published on Slideshow
Static slideshow
Download PDF version
Download PDF version
Embed video
Share video
Ask about this video

Scene 1 (0s)

[Audio] To BOSS ABG, MADAM RBG, Operation Manager TJS, Project Managers, Co-Project Engineers, Department heads present, and to all, pleasant greetings from PORT OF CLAVERIA team. In the name of our project manager Engineer Ruben B Manrique and my co-project engineer Charlene Joy Antiga, allow me to present to you our week update for the project Rehabilitation/Improvement of Claveria Port Project as of June 16, 2022. Presenting now is Engineer Jeomar A Bautista..

Scene 2 (36s)

[Audio] This slide shows the project time elapse as of the date. As reflected, the project has already lapsed 344 calendar days, we are at middle period of the project contract, having an actual accomplishment of 63.941% versus the programmed accomplishment of 64.630% , having a slippage of negative 0.691[break]%.

Scene 3 (1m 15s)

[Audio] The next slide shows the statement of work accomplishment. This slide reflects the actual project movement per payable item. Those boxed item are the active activities in the previous week..

Scene 4 (1m 46s)

[Audio] Again, those boxed item are the items having an accomplishment for the past week. As per table, most active items are under bill number 3 under back up are with roro ramp fill..

Scene 5 (2m 21s)

[Audio] To show the summary, same as the one reflected on the time elapsed, we have a negative slippage of 0.690% compared to last week which is positive 0.078[break]%.

Scene 6 (2m 48s)

[Audio] In particular, bill number 2, item 2.06 : Extraction of existing rocks/ structures prior to the construction of anchor wall, and item 2.07: Removal of existing concrete blocks prior to the installation of anchor wall and sheet piles is an active item last week..

Scene 7 (3m 11s)

[Audio] Moreover, under bill number 3, item 3.03: Supply and Install Steel Waling and Splice Plates for Sheet Piles , Item 3.04 : Removal of existing concrete blocks prior to the installation of anchor wall and sheet piles.

Scene 8 (3m 31s)

[Audio] Item 3.05: Supply and Install Tie-Rod of Various Sizes at 60 mm x 12 meters Length, Item 3.06: Supply and Place 3, 500 psi Concrete for Retaining Walls.

Scene 9 (3m 51s)

[Audio] Item 3.07: Supply and Install Steel Reinforcements to Retaining Walls, Item 3.10: Supply and Install Geotextile Fabric.

Scene 10 (4m 6s)

[Audio] Item 3.11: Supply and Place Sand and Gravel Fill, and Item 3.15: Supply and Place Aggregate Base Course, are the moving items last week..

Scene 11 (4m 21s)

OF. ITEM 2.06: EXTRACTION PRIOR TO LAYING OF ANCHOR WALL.

Scene 12 (4m 36s)

ITEM 2.07: REMOVAL OF EXISTING CONCRETE BLOCKS. Picture Update.

Scene 13 (4m 49s)

pus • lie: lie: STEEL •. ITEM 3.03: SUPPLY AND INSTALL STEEL WALING.

Scene 14 (5m 1s)

1-0,. OWS. suns. abstract. ITEM 3.03: SUPPLY AND INSTALL STEEL WALING.

Scene 15 (5m 12s)

LEO St STEEL •EEO STEEL as' 'ENCTH STEEL • SSSI TE STEEL.

Scene 16 (5m 24s)

. Of. ITEM 3.04: CUTTING OF NEWLY DRIVEN PILES. Picture Update.

Scene 17 (5m 38s)

ROLLED STEEL pus s STEEL TIE ROO STEEL RCO 'PACO STEEL as) a RECTO' (SEE TIE ROO space g STEEL LENGTH STEEL SHEET PILES • • IIÄ: TIE *ACED g a. — Z. HOT SHEET.

Scene 18 (5m 57s)

. - 'iiiiii.iiiiiiäiéöä$i€. ITEM 3.05: SUPPLY AND INSTALL TIE ROD.

Scene 19 (6m 12s)

GOG. ITEM 3.05: SUPPLY AND INSTALL TIE ROD. Picture Update.

Scene 20 (6m 25s)

STEEL Oø 00 sex:soa 47m m STEEL Si-€ET mSS • SES' Oø • a STEEL NOTE: VACANT CREW WILL BE UTILIZED IN OTHER ACTIVITIES z ',zm w," wm ',zmv//.a w," vm w rum ROO •ee@ TE @ STEEL z.ryPE s.«r •.

Scene 21 (6m 52s)

ITEM 3.06: SUPPLLY AND PLACE 3, 500 PSI CONCRETE.

Scene 22 (7m 8s)

ITEM 3.06: SUPPLLY AND PLACE 3, 500 PSI CONCRETE.

Scene 23 (7m 30s)

ITEM 3.06: CONCRETE POURING ACTIVITIES. Picture Update.

Scene 24 (7m 42s)

ITEM 3.06: CONCRETE POURING ACTIVITIES. Picture Update.

Scene 25 (7m 52s)

ITEM 3.06: CONCRETE POURING ACTIVITIES. Picture Update.

Scene 26 (8m 3s)

ITEM 3.06: CONCRETE POURING ACTIVITIES. Picture Update.

Scene 27 (8m 11s)

STEEL Oø 00 sex:soa 47m m STEEL Si-€ET mSS • SES' Oø • a STEEL NOTE: VACANT CREW WILL BE UTILIZED IN OTHER ACTIVITIES z ',zm w," wm ',zmv//.a w," vm w rum ROO •ee@ TE @ STEEL z.ryPE s.«r •.

Scene 28 (8m 32s)

flb.pu_) puv. ITEM 3.07: SUPPLY AND INSTALL STEEL REINFORCEMENT.

Scene 29 (8m 44s)

ii'üiliii' -. ITEM 3.07: SUPPLY AND INSTALL STEEL REINFORCEMENT.

Scene 30 (8m 52s)

AGRA. ITEM 3.10: SUPPLY AND INSTALL GEOTEXTILE FABRIC.

Scene 31 (9m 3s)

ITEM 3.11: SUPPLY AND PLACE SAND AND GRAVEL FILL.

Scene 32 (9m 19s)

ITEM 3.11: SUPPLY AND PLACE SAND AND GRAVEL FILL.

Scene 33 (9m 29s)

OTHER. SITE. RELATED. ACTIVITIES.

Scene 34 (9m 37s)

ilJDÜn-. ITEM 3.07: PLASTERING WORKS. Picture Update.

Scene 35 (9m 47s)

PROJECT EXPENSES.

Scene 36 (9m 56s)

BILLING STATUS. Joint Ventu re HI-TONE AND DEVELOPMENT CORPORATION Sto. . A PROJECT BILLING STATUS AS OF JULY, 2022 Remaning Collectible Projed Amcunt First Billing RETENTION 1 Second Billing March25, 2022 Third Billing Forth Billing Billing 23 736% 35 334% 44 865% 50978% Cdleded Amount + VAT PHP PHP PHP PHP PHP Dde 3), Z)21 DecemtH 1 , 2021 DecemtH 13, 2021 June9, 2022 PHP PHP PHP PHP PHP Amount 70 45 65.

Scene 37 (10m 13s)

EQUIPMENT STATUS. Equipment Breakdown: 2-Units Jackhammer 1-Unit Submersible Pump 2- Unit Generator 1-Unit Concrete Vibrator.

Scene 38 (10m 30s)

PROJECT CONCERNS. ENGINEERING DIV. / ACCOUNTING. Pending Payables for Various Hardware Materials under RJJ Aristotle Trading – 63 k.

Scene 39 (10m 42s)

PROJECT CONCERNS. ENGINEERING DIV. / Purchasing Dep’t.

Scene 40 (10m 56s)

GIFs For Powerpoint Presentation - 100 Pieces of GIF Animation.

Scene 41 (11m 4s)

Either you RUN the day or the day RUNS you..

Scene 42 (11m 13s)

S T A Y H E A L T H Y !. GOD BLESS KKCCDC !. GOD BLESS KKCCDC !.