Scene 1 (0s)

BRIDGEPORT CONSTRUCTION UPDATES. DECEMBER 1, 2025.

Scene 2 (9s)

1. BUILDING A. (AZURE) TURN OVER DATE REMARKS/STATUS 1.1 FINAL PUNCHLIST (COMMON AREAS) NOVEMBER 2025 DONE RECTIFY/FOR CHECKING BY ANFLOCON AND DLI 1.2 OPERATION MANAGEMENT MANUALS (OPMM) NOVEMBER 2025 DONE RECTIFY/FOR CHECKING BY ANFLOCON AND DLI 1.3 AS BUILT PLANS NOVEMBER 2025 FOR BLUEPRINT AND SIGN AND SEAL.

Scene 3 (34s)

3. LINEAR POOL TURN OVER DATE REMARKS/STATUS 3.1 FINAL PUNCHLIST (COMMON AREAS) NOVEMBER 2025 DONE RECTIFY/FOR CHECKING BY ANFLOCON AND DLI 3.2 AS BUILT PLANS DECEMBER 10,2025 FOR BLUEPRINT AND SIGN AND SEAL.

Scene 4 (57s)

5. BUILDING B. (SAPHIRE) ACTUAL PHOTOS. fi15:59 hilippines.

Scene 5 (1m 6s)

LZ:OL ZVLCSZOZ I leuue. Davao City 1 2025.11.12 10:23 •g 'Illi.

Scene 6 (1m 18s)

SV:OL ZCLCSZO !tj-oezxea. 202511.12 10:48. Davao City 1 202511.12.

Scene 7 (1m 28s)

TURN OVER STATUS. PUNCHLIST MONITORING WORKS OF BUILDING B SAPPHIRE BUILDING -GROUND FLOOR STATUS LOPZCOM RECTIFY OF AREA AREA 1 AREA 2 AREA 3 AREA 4 AREA AREA 1 AREA 2 AREA 3 AREA 4 AREA 5 AREA 6 UNIT 105 106 107 108 109 110 111 112 115 116 117 118 119 UNIT 207 210 211 212 215 216 217 218 219 221 222 201 203B UNITS DONE RECTIFICATION FOR m FOR IPL FOR IPL FOR IPL FOR IPL FOR IPL FOR IPL FOR IPL FOR IPL FOR IPL FOR IPL FOR IPL FOR IPL FOR IPL FOR IPL UNITS DONE RECTIFICATION FOR IPL FOR IPL FOR IPL FOR IPL FOR IPL FOR IPL FOR IPL FOR IPL FOR IPL FOR IPL FOR IPL FOR IPL FOR IPL FOR IPL FOR IPL FOR IPL FOR IPL FOR IPL FOR IPL FOR IPL FOR IPL FOR IPL 2ND 1ST RECHECKING TARGET IPL DATE SEPT. 08, 2025 SEPT. 08, 2025 SEPT. 08, 2025 SEPT. 08, 2025 SEPT. 09.2025 SEPT. 09, 2025 SEPT. 09, 2025 SEPT. 09, 2025 SEPT. 10, 2025 SEPI 10, 2025 SEPT. 10.2025 SEPT. 11, 2025 SEPT. 11.2025 SEPT. 11, 2025 TARGET DATE OCT. 29, 2025 OCT. 29, 2025 OCT. 29.2025 OCT. 29, 2025 NOV. 05, 2025 NOV. 05, 2025 NOV. 05, 2025 NOV. 05, 2025 NOV. 12, 2025 NOV. 12, 2025 NOV. 12, 2025 NOV. 11, 2025 NOV. 11, 2025 NOV. 11, 2025 NOV. 10, 2025 NOV. 10, 2025 NOV. 10, 2025 07, 2025 NOV. 07, 2025 07, 2025 NOV. 07, 2025 ACTUAL IPL DATE SEPT. 09, 2025 SEPT 09, 2025 SEPT. 09, 2025 SEPT. 09, 2025 SEPT. 16, 2025 SEPT. 17, 2025 SEPT. 17, 2025 SEPT. 24, 2025 SEPT 23, 2025 SEPT. 24, 2025 SEPT. 30, 2025 SEPT. 30, 2025 SEPT 29, 2025 DATE TRANSMITTED OCT. 22.2025 OCT. 22, 2025 OCT. 22.2025 OCT. 22, 2025 NOV. 08.2025 NOV. 08, 2025 NOV. 08.2025 NOV. 08, 2025 NOV. 08.2025 NOV. 08, 2025 NOV. 08.2025 NOV. 08, 2025 NOV. 08.2025 NOV. 08, 2025 DATE TRANSMITTED NOV. 26, 2025 NOV. 21, 2025 NOV. 21, 2025 NOV. 21, 2025 NOV. 21, 2025 NOV. 21, 2025 TO TRANSMIT TO TRANSMIT TO TRANSMIT NOV. 27, 2025 TO TRANSMIT NOV. 21, 2025 TO TRANSMIT TO TRANSMIT TO TRANSMIT TARGET CLOSE-OUT NOV. 17, 2025 NOV. 17, 2025 NOV. 17, 2025 NOV. 17, 2025 NOV. 21, 2025 NOV. 21, 2025 NOV. 21, 2025 NOV. 21, 2025 NOV. 11, 2025 NOV. 11, 2025 NOV. 11, 2025 NOV. 12, 2025 NOV. 12, 2025 NOV. 12, 2025 ACTUAL CLOSE-OUT NOV. NOV. SEPT . 16, 2025 NOV. 14, 2025 NOV. 14, 2025 NOV. 18, 2025 NOV. 18, 2025 NOV. 18, 2025 NOV. 18, 2025 NOV. 18, 2025 14, 2025 14, 2025 IPL (DONE) FOR RECHECKING/DONE FOR RECHECKING/DONE FOR RECHECKING/DONE FOR RECHECKING/DONE FOR RECHECKING/DONE FOR RECHECKING/DONE FOR RECHECKING/DONE FOR RECHECKING/DONE FOR RECHECKING/DONE FOR RECHECKING FOR RECHECKING/DONE FOR RECHECKING/DONE FOR RECHECKING/DONE FOR RECHECKING/DONE OF IPL (DATE) 11/11/2025 11/11/2025 11/11/2025 11/11/2025 11/14/2025 11/14/2025 11/18/2025 11/18/2025 11/18/2025 RECHECKING OF IPL DATE 11/14/2025 11/14/2025 11/14/2025 11/14/2025 11/18/2025 11/18/2025 11/26/2025 11/26/2025 11/26/2025 STATUS RECHECKING DONE FOR F.C.O. FOR FCO FOR FCO FOR FCO FOR FCO FOR FCO FOR FCO FOR FCO FOR FCO FOR FCO STATUS FCOICCO STATUS FCO DONE FCO DONE FCO DONE FCO DONE FCO DONE FCO DONE FCO DONE FCO DONE FCO DONE PUNCHLIST MONITORING WORKS OF BUILDING B SAPPHIRE BUILDING -2ND FLOOR STATUS LOPZCOM RECTIFY OF 11/26/2025 11/18/2025 11/18/2025 11/18/2025 2ND 1ST RECHECKING REMARKS DLI/ANFLOCON ACCEPTED DLI/ANFLOCON ACCEPTED DLI/ANFLOCON ACCEPTED DLI/ANFLOCON ACCEPTED DLUANFLOCON ACCEPTED DLI/ANFLOCON ACCEPTED DLI/ANFLOCON ACCEPTED DLI/ANFLOCON ACCEPTED DLI/ANFLOCON ACCEPTED REMARKS ACTUAL IPL DATE OCT. 29, 2025 OCT. 29, 2025 OCT. 29, 2025 OCT. 29, 2025 NOV. 05, 2025 NOV. 05, 2025 NOV. 18, 2025 NOV. 18, 2025 NOV. 25, 2025 NOV. 19, 2025 NOV. 20, 2025 NOV. 05, 2025 NOV. 10, 2025 NOV. 11, 2025 NOV. 11, 2025 TARGET CLOSE-OUT NOV. 14, 2025 NOV. 14, 2025 NOV. 14, 2025 NOV. 14, 2025 NOV. 17, 2025 NOV. 17, 2025 NOV. 18, 2025 NOV. 18, 2025 NOV. 24, 2025 NOV. 24, 2025 NOV. 24, 2025 NOV. 21, 2025 NOV. 21, 2025 NOV. 21, 2025 NOV. 19, 2025 NOV. 19, 2025 NOV. 19, 2025 NOV. 17, 2025 NOV. 18, 2025 NOV. 18, 2025 NOV. 18, 2025 ACTUAL CLOSE-OUT RECHECKINGOF RECHECKING DONE IPL (DATE) FOR RECHECKING FOR RECHECKING FOR RECHECKING FOR RECHECKING FOR RECHECKING FOR RECHECKING FOR RECHECKING OF IPL (DATE) IPL DATE FOR F.C.O..

Scene 8 (4m 16s)

WORKS OF BUILDING B 2ND STATUS AREA AREA 1 AREA2 AREA3 AREA4 AREA5 AREA6 UNIT 305 306 307 308 309 310 311 312 315 316 317 318 319 320 321 322 323 301 302 303A 303B UNITS DONE RECTIFICATION FORIPL FOR FOR FOR IPL FOR IPL FOR IPL FOR ON GOING FOR IPL FOR IPL FOR IPL FOR FOR FOR IPL FOR IPL FOR IPL FOR FOR FOR IPL ON GOING FOR IPL ON GOING SAPPHIRE BUILDING FLOOR STATUSLOPZCOMRECTIFYOF 1ST RECHECKING ACTUAL CLOSE-OUT (DATE) TARGET NOV. 17, 2025 NOV. 17, 2025 NOV. 17, 2025 NOV. 17, 2025 NOV. 18, 2025 NOV. 18, 2025 NOV. 18, 2025 NOV. 18, 2025 NOV. 19, 2025 NOV. 19, 2025 NOV. 19, 2025 NOV. 21, 2025 NOV. 21, 2025 NOV. 21, 2025 NOV. 24, 2025 NOV. 24, 2025 NOV. 24, 2025 NOV. 2025 NOV. 14, 2025 NOV. 14, 2025 NOV. 14, 2025 ACTUAL m DATE NOV. 26, 2025 DATE TRANSMITTED TO TRANSMIT TARGET CLOSEOUT NOV.26,2025 NOV.26,2025 NOV.26,2025 NOV.26,2025 NOV.28,2025 NOV.28,2025 NOV.28,2025 DEC. 01, 2025 DEC. 01, 2025 DEC. 01, 2025 DEC. 02, 2025 DEC. 02, 2025 DEC. 02, 2025 DEC. 03, 2025 DEC. 03, 2025 DEC. 03, 2025 NOV.25,2025 NOV. 25,2025 NOV.25,2025 NOV.25,2025 RECHECKINGOF RECHECKING DONE OFIPL(DATE) m (DATE) FOR F.C.O REMARKS.

Scene 9 (5m 2s)

PUNCHLIST MONITORING WORKS OF BUILDING B SAPPHIRE BUILDING 4TH FLOOR 2ND STATUSLOPZCOMRECTIFYOF ISTRECHECKING STATUS AREA AREAI AREA2 AREA3 AREA4 AREAS AREA6 UNIT 505 506 507 508 509 510 511 512 515 516 517 518 519 520 521 522 523 501 502 503A 503B UNITSDONE RECTIFICATION FORIPL ON GOING FOR FOR ONGOING ONGOING WT ONGOING ONGOING WT ONGOING TARGET IPLDATE NOV.27,2025 NOV.27,2025 NOV.27,2025 NOV.27,2025 NOV.28,2025 NOV.28,2025 NOV. 28, 2025 NOV.28,2025 DEC. 01, 2025 DEC, 01, 2025 DEC. 01, 2025 DEC. 02, 2025 DEC. 2025 DEC. 03,2025 DEC. 03, 2025 DEC. 03, 2025 NOV.25,2025 NOV.25,2025 NOV.25,2025 NOV.25,2025 ACTUAL IPLDATE NOV.20,2025 NOV. 20,2025 DATE TRANSMITTED NOV. 26,2025 NOV. 26,2025 TARGETCLOSEOUT ACTUALCLOSE.OUT RECHECKINGOF RECHECKING DONE OF m (DATE) FORF.C.O. IPL(DATE) REMARKS IPL (DATE) DEC. 08, 2025 DEC, 08, 2025 DEC. 08, 2025 DEC. 08, 2025 DEC. 09, 2025 DEC. 09, 2025 DEC. 09, 2025 DEC. 09, 2025 DEC. 10, 2025 DEC, 10, 2025 DEC, 10, 2025 DEC. 12, 2025 DEC. 12, 2025 DEC, 12, 2025 DEC. 15, 2025 DEC. 15, 2025 DEC. 15, 2025 DEC. 05, 2025 DEC, 05, 2025 DEC. 05, 2025 DEC. 05, 2025.

Scene 10 (5m 49s)

6. BUILDING C.. PROJECT TIMELINE DATE Construction start August 4, 2025 Project completion October 21, 2026 PROJECT DURATION TOTAL NO. OF DAYS PERCENTAGE Construction duration 456 CD Days elapsed 118 Days 25.87% Days to go 338 Days 74.13%.

Scene 11 (6m 12s)

Samal 2025.11.26 11:00. 2025.11.2 1:02. Davao City 2025.11.26 11:04 . jil•" , ;.

Scene 12 (6m 26s)

SCOPE OF WORKSS REL.WT ACTUAL POC (%) SCHEDULE POC (%) DIFFERENCE POC (%) GENERAL REQUIREMENTS 9.16% 2.38% 2.33% 0.06% SURVEY & EARTHWORKS 1.70% 1.68% 1.70% -0.01% FOUNDATION WORKS 4.49% 4.43% 4.49% -0.06% REINFORCED CONCRETE WORKS 16.75% 8.97% 8.72% 0.25% ROOF FRAMING WORKS 0.68% 0.00% 0.00% 0.00% ROOFING & ACCESSORIES 2.12% 0.00% 0.00% 0.00% CEILING PARTITIONS 2.25% 0.16% 0.25% -0.09% DRYWALL PARTITIONS 0.27% 0.01% 0.03% -0.02% WALL & CEILING MOULDING 1.43% 0.08% 0.16% -0.08% BASE BOARDS & DRIP MOLD 1.03% 0.05% 0.12% -0.06% HALLWAY/CORRIDOR RAILINGS 1.68% 0.00% 0.00% 0.00% BALCONY RAILINGS & STEEL LOUVERS 0.78% 0.00% 0.00% 0.00% ELEVATOR SEPARATOR BEAM 0.08% 0.00% 0.00% 0.00% PAINTING WORKS 7.00% 0.28% 0.39% -0.11% FLOOR TILES 7.70% 0.00% 0.00% 0.00% WATER PROOFING 0.70% 0.00% 0.03% -0.03% SEISMIC GAP 0.40% 0.00% 0.00% 0.00% TANK 0.69% 0.48% 0.29% 0.19% PLUMBING WORKS 3.26% 2.24% 0.69% 1.55% SANITARY FIXTURES 2.00% 0.00% 0.00% 0.00% FIRE PRO 3.03% 0.75% 0.00% 0.75% PUMP MOTORS 4.40% 0.19% 0.00% 0.19% ROUGHING-INS 2.28% 0.86% 0.49% 0.38% WIRES - UNIT 1.61% 0.00% 0.00% 0.00% WIRES - HALLWAY/CORRIDOR 0.21% 0.00% 0.00% 0.00% WIRES - FEEDER LINE 1.72% 0.00% 0.00% 0.00% WIRES - MCP PUMPS 0.10% 0.00% 0.00% 0.00% WIRES - ROYAL CORD & NEUTRAL LINE 0.05% 0.00% 0.00% 0.00% PANELBOARD & BREAKERS - UNIT 0.41% 0.11% 0.00% 0.11% PANELBOARD & BREAKERS - MAIN & COMMON 1.25% 0.00% 0.00% 0.00% SWITCH, OUTLETS & LIGHTINGS FIXTURES 3.09% 0.00% 0.00% 0.00% AUXILIAR, FDAS, CCTV, - WIRES & ROUGHING INS 0.81% 0.20% 0.19% 0.01% FDAS - FIXTURES, DEVICES & ACCESSORIES 1.43% 0.00% 0.00% 0.00% TOTAL POC 100.00% 26.87% 23.79% 3.08% ACTUAL POC AS PER SCHED..

Scene 13 (8m 15s)

BRIDGEPORT PARK FOUR (4) STOREY CONDOMINIUM BUILDING C ACTUAL POC = 26.87 % ; SCHED. = 23.79 % 100.00% 90.00% 80.00% 70.00% 60.00% 50.00% 40.00% 30.00% 20.00% 10.00% 0.00% CONDOMINIUM BLDG. C (ROYAL) 26.87% 23.79% A-GUST 20 2025- m6.

Scene 14 (8m 30s)

MAN POWER. AREAS NO. OF WORKERS REMARKS BUILDING A. 6 PUNCHLIST WORKS (PAINTING WORKS) BUILDING B. 75 PUNCHLIST WORKS/GROUT/CLEANING BUILDING C. 133 STRUCTURAL,ARCHITECTURAL AND MEPFS WORKS CLUB HOUSE 4 PUNCHLIST WORKS AND WELDING WORKS ADDITIONAL LINEAR POOL/BATHOUSE/GAZEBO 2 PUNCHLIST WORKS TOTAL MAN POWER 220.

Scene 15 (8m 47s)

BULDING C. MATERIAL STATUS. MATERIALS PAYMENT STATUS STATUS/DELIVERY SCHEDULE FLOOR TILES 200X1200 Paid Waiting for the arrival December 2025 FLUTED TILES Done Dp Requested HALLWAY TILES 60X60 Requested CR WALL AND FLOOR TILES 60X60 Requested BALCONY FLOOR TILES 60X60 Requested SUBWAY TILES Requested F-DAS No Payment FIRE PROTECTION 25% DP PUMPS 20% DP December 18,2025 TANKS 30% DP December 18,2025 GLASS 20% DP STAINLESS RAILINGS Request for Fabrication ELECTRICAL PANELS 10% DP ELECTRICAL WIRES No Payment WATER PROOFING (DAVCO) Partial materials on-site PAINTING MATERIALS Partial materials on-site LIGHTNING ARRESTER 50% DP CARPENTRY MATERIALS Partial materials on-site.

Scene 16 (9m 14s)

THANK YOU! .