[Audio] Welcome to Woqod, Now we are here for HSE induction for Bitumen operations..

Scene 2 (9s)

[Audio] Welcome to Bitumen plant facility. It is part of Woqod Site Safety management that all Staff, Visitor and Contractors planning to enter Bitumen Plant should undergo site induction before proceeding. Woqod has an Integrated Management System (IMS) Policy which covers an integrated approach for achieving and sustaining Operational Excellence through our commitment to: Strive for Zero Harm to our personnel and neighbors, Safeguard the environment in which we operate Maintain the operational integrity and security of our assets. Deliver high quality in our Services and products to our customers Fully comply with Qatari laws, regulation, and regional/International protocols and agreements applicable to our business operations Contribute to the social development of Qataris as a Corporate Citizen..

Scene 3 (1m 6s)

[Audio] Safety Alert In case of EMERGENCY or FIRE, all personnel (employees, contractors) must leave their workplace and must assemble to the nearest and safest Assembly Point. Stay Calm, don't run and Don't panic Ensure to take time to check the Floor Warden and First Aider posters in order to be aware of who the Floor Wardens and First Aiders are for a specific building names are displayed in each building. Important Emergency Contacts Numbers are as follows: MIC Control room 135 Control Room 40218136/8303 Bitumen Supervisor 40218311 Security 40218015 HSE OFFICER- 021-8391 You will be Updated, if any Mock drill plan to attendee during induction..

Scene 4 (2m 9s)

[Audio] In the given picture, which is the "Layout for emergency exit and Assembly point. Follow the direction as well as the instructions from the floor warden..

Scene 5 (2m 21s)

[Audio] In 'bitumen facility' we have Bitumen Operations are run from Mesaieed Industrial City (MIC) port area. The raw bitumen is received through WOQOD Marine ships from Various Countries and using 8" piping through pipe rack and is pumped to 06nos of 2500m3 capacity storage tanks in the Bitumen plant All the bitumen & PMB tanks heated through Thermax system using thermic fluid The Electrical Heat Tracing System is designed to ensure that the Bitumen/PMB is always maintained in a fluidized state in the pipeline to enable smooth functioning of the entire plant And also, Bitumen is transported to customers via road tankers. Bitumen is transported at a high temperature of 140 C. Other Bitumen are modified into other product, Cutback (MC 70), Polymer Modified Bitumen (PMB).

Scene 6 (3m 23s)

[Audio] You can see the lift for the existing facilities available with "Bitumen facility"..

Scene 7 (3m 30s)

[Audio] The most significant hazard to workers who deal with hot bitumen is the potential to cause burns in case of splashes or spills. Bitumen is usually applied hot. Hot bitumen gives off emissions that can cause minor respiratory tract or eye irritation after prolonged, close exposure Considering the Bitumen facility activities, following nature of emergencies may occur: Major fire on Diesel & Kerosene tanks. Oil spillage with and without Fire Hot surfaces (e.g. heaters, Product pipelines) Hot Bitumen Over flow of bitumen Bitumen spillage/Foaming Vehicle movement. Rotating equipment Exposure to dust/ heat/ hot bitumen emissions Trip/ slip/ fall Natural calamity leading to disturbance of operation.

Scene 8 (4m 33s)

[Audio] Common Hazards are as follows ; Fire Inhalation (due to long time exposures) Skin contacts Contact with eyes.

Scene 9 (4m 47s)

[Audio] Vehicle movement Dust Equipment rotation or moving parts And Slippery or obstructed pavement or floors.

Scene 10 (5m 1s)

[Audio] In case of emergency action For the First Aid Bitumen burns should be cooled for at least 20 minutes, first with cool water to reduce pain, then with warm water to prevent hypothermia if the burned surface is larger than the size of a hand. Burns to the eyes should be irrigated for at least 5 minutes. Please follow the standard First Aid procedure and shall be implemented by the competent person only..

Scene 11 (5m 31s)

[Audio] For the Bitumen plant area A PPE matrix has been implemented; all persons shall follow it as per their roles and area of activities. Personal Protective Equipment (PPE) Matrix are posted in the premises in Various Location, and all WOQOD staff, contractors and visitors must comply by wearing the required personal protective equipment (PPE) wherever applicable. Personal Protective Equipment (PPE),Applies to all WOQOD staff/ Visitors/ Contractor In addition to the PPE Matrix requirement, personnel shall comply with other PPEs that might be required by the permit to work and or job safety analysis..

Scene 12 (6m 17s)

[Audio] PPE shall be used when working with bitumen and shall cover all parts of exposed skin to avoid direct contact. Loading and unloading always use following PPE: Personal Protective Equipment must be worn when handling hot liquid product Protective Clothing & Equipment: - High Visibility Coverall Hand Gloves(Heat Resistant type) * Head Protection * Neck or Face Protection Protective Footwear..

Scene 13 (6m 51s)

[Audio] In case of any fire incident Try to Extinguish by using portable Fire Extinguisher If the fire is within control, attempt to extinguish, it with the appropriate fire extinguisher. Method of using your own fire extinguishers Stand back 6 to 8 feet from fire For portable fire extinguisher, the PASS procedure for the usage shall be followed. PASS is Pull the pin. Aim the fire base. Squeeze the lever Sweep from side to side.

Scene 14 (7m 31s)

[Audio] Heat Stress Management Woqod s Heat Stress Management system provides a detailed guidance on assessing and monitoring personnel who may at risk of heat stress during their normal duties. Woqod Bitumen staff is measuring heat stress index value and communicated to all through Heat stress flag posted in bitumen plant in dedicated locations Flagging system Verbal communication Sharing Heat Index value through WhatsApp All the employees, contractors/Visitors are advised to take the precautionary measures mentioned against heat index..

Scene 15 (8m 11s)

[Audio] For HSE observation As part of our commitment to Safety, you have the right to stop work and report any activity you consider to be unsafe. As a proactive approach in preventing accidents, HSE Observation reporting is in place. Staff, contractors, and visitors can report unsafe actions and conditions either through HSE observation cards or through the eWOQOD WOQOD HSE observation portal..

Scene 16 (8m 42s)

[Audio] Smoking is strictly NOT allowed inside the Bitumen facility other than the designated areas only..

Scene 17 (8m 50s)

[Audio] General Safety rules Which we follow in bitumen are as follows Photography without valid photographic permit not allowed Potential ignition sources like open flame, smoking, or use of non-intrinsically safe device are strictly prohibited in the Plant's Operations area Work with Valid work permit Follow the WOQOD approved PPE matrix Follow the WOQOD life saving rule Follow the Driving guideline Don't horseplay at work site Follow the emergency response plan procedure when required. Evacuate the area in case of hearing the emergency alarm proceed to AP. Do not the leave the vehicle unattended with engine on Driving and vehicle movement is a hazard, hence always observe the speed limit while driving within the Plant premises. Maintain good house keeping in the plant.

Scene 18 (9m 55s)

[Audio] In bitumen plant We have General driving rules The driver must follow the traffic warning and caution signs. The driver must follow the plant speed limit 15 Kilometer per hour The driver must follow correct traffic flow. Don't park or queue at non designated parking or queuing areas. Park only a proper designated area Smoking is prohibited at all times in vehicles. Reverse parking policy is strictly implemented in the Plant. Be extra cautious especially while reversing. Please follow the all standard safety precautions for the Safe driving.